Site-Interface Responsibility Register
Assign a proposed owner to each interface. “Joint review” is useful during quotation, but the contract should name one accountable party for each deliverable.
Utility connection and protection settings
Single-line diagram and equipment boundary
Foundation, trench and cable-entry geometry
Grounding study, grid and bonding points
Fire, fluid containment and drainage criteria
Transport route, lifting and unloading
Site installation and termination
Inspection, energization and handover records