Submittal control

Transformer Approval Evidence Register

Track the minimum evidence needed to move a transformer order from design review through release and acceptance. Statuses describe your project record only and do not claim that a document has been supplied by Talite.

Accepted evidence

0%

Status logic

  • Required: identified but not submitted
  • Submitted: received, review pending
  • Accepted: reviewed for the project stage
  • Hold: discrepancy blocks progression
Evidence item Typical control point Project status
Approved technical data sheet Bid alignment
General arrangement and interface drawing Design approval
Nameplate and rating diagram Design approval
Control, alarm and wiring schematic Design approval
Bill of materials or component schedule Design freeze
Quality plan and inspection/test plan Pre-production
Routine test procedure and acceptance criteria Pre-test
Special or witnessed test procedure Pre-test
Routine test report Release
Packing, lifting and transport plan Shipment release
Installation, operation and maintenance manual Site readiness
Spares and final document index Handover

Open controls

  • Set the current status for each evidence item.