Loss-Capitalized Quote Normalization Worksheet
Loss-Capitalized Quote Normalization Worksheet
Enter the values from two controlled supplier offers. The worksheet combines purchase price with buyer-owned loss coefficients so unlike bids can be reviewed on one stated basis.
Buyer evaluation coefficients
Use coefficients approved for your project. Currency must be consistent across every field.
Supplier Bid Quotations
Supplier A
AEvaluated bid value
Supplier B
BEvaluated bid value
Worksheet result
The lower calculated value is highlighted only when both offers contain enough numeric inputs. Technical compliance, contractual scope and evidence still require separate review.
Current comparison
Enter both offers
No evaluation is made from blank or zero-only inputs.
Calculation boundary
- The buyer supplies A, B and C; the tool does not estimate electricity prices, duty cycles or service life.
- Use guaranteed loss values measured and accepted under the contract’s stated test basis.
- Normalize included accessories, testing, freight, installation and commissioning before treating two totals as comparable.
Start with one approved currency. Procurement enters the commercial values exactly as offered. Engineering confirms the guaranteed losses and test basis. Finance owns the capitalization coefficients used for evaluation. Any scope exception belongs in the clarification register. Results remain in this browser page and are not sent to Talite Transformer.
This worksheet is a bid-normalization aid, not an engineering design, financial forecast or recommendation. Confirm the method, coefficients, currency and contract scope with the responsible professionals.