Delivery Programme Planner
Delivery Programme Planner
Builds the whole programme, not just the factory window: drawing approval, build, ocean transit and inland movement. It is a planning estimate for your schedule, and the binding dates come from the quotation.
Planning Parameters
Factory windows are the published Talite figures: 20 to 45 days ex-works for distribution-class units up to 2,500 kVA once drawings are approved. Power-class units from 110 kV are scheduled per project, so this planner shows a placeholder band for them and flags it rather than inventing a number.